CreatingWBSmeanssubdividingthemajorprojectdeliverablesintosmallercomponentsuntilthedeliverablesaredefinedtothelevel()

来源: 计算机软件水平考试    技能等级   

CreatingWBSmeanssubdividingthemajorprojectdeliverablesintosmallercomponentsuntilthedeliverablesaredefinedtothelevel()

A、independentresource

B、individualworkload

C、workmilestone

D、workpackage